September 2022: Tenative Construction Timeline Created
Tentative pre-construction/construction timeline is developed with consideration of the liturgical calendar, the climate and the organ:
January – March 2023 Pre-construction design work
April – September 2023 Phase I: HVAC (to begin after Easter Sunday)
October 2023 – February 2024 Phase II: Undercroft finishing
April – August 2024 Phase III: Sanctuary refinishing (to begin after Easter Sunday)